January 26, 2017 -- Please note that the construction of the Esplanade hoarding (over the sidewalk) is scheduled to commence this Thursday January 26.
December 1, 2016 to February 15, 2017 -- Demolition of 127 to 131 West Esplanade including hazardous material abatement. It is not anticipated that traffic will be impacted by the work.
Tuesday March 14th – Site Servicing crews mobilze and commence utility locates
Monday March 20th –Work commencement on Rogers Avenue. The Rogers Avenue works is expected to take 6 to 7 working days.
Week of March 27th -- Carrie Cates Court – work expected to take approx. 9 working days
Week of April 3rd – Mews Lane (backing onto businesses) – work is expected to take 6 to 7 working days
May 22nd - On May 22nd we will commence on-site bulk excavation, which should take approximately 3 to 4 months. The excavation work will be contained within our property and trucks will be loaded on-site.